The Transmission Company of Nigeria (TCN) has successfully completed the relocation of eight transmission towers along the Kukwaba/Apo 132kV transmission line in the Federal Capital Territory (FCT), restoring full power to the Apo Transmission Substation. This achievement comes three days after the initially projected completion date of January 20, 2025. The relocation project, which commenced on January 6, 2025, was necessitated by the Federal Capital Development Authority’s (FCDA) road dualization project along the Apo axis. The successful completion of this project signifies a crucial step in infrastructural development within the FCT, balancing the needs of both the power sector and ongoing road expansion efforts.
The relocation process entailed the dismantling and reconstruction of eight transmission towers, encompassing both 132kV and 33kV structures. This complex undertaking also involved restringing the power cables along the newly positioned towers to ensure the seamless flow of electricity from the Gwagwalada Substation to the Apo Transmission Substation. The TCN had initially anticipated a two-week timeline for this project, involving daily power outages from 9 am to 4 pm. The slight delay in completion, while minimal, underscores the intricate nature of the task and the TCN’s commitment to ensuring the structural integrity and safety of the newly erected towers.
The restoration of full bulk power to the Apo Transmission Substation is a significant development for residents and businesses in the affected areas, marking the end of a period of planned power outages and load rationing. The Abuja Electricity Distribution Company (AEDC) can now resume normal electricity supply to its customers, relieving them from the inconvenience experienced during the relocation period. The TCN’s proactive communication throughout the process, including the initial announcement of the planned outage and the subsequent confirmation of power restoration, demonstrates its dedication to transparency and keeping the public informed.
The successful relocation project underscores the importance of inter-agency collaboration in infrastructure development. The TCN’s coordinated efforts with the FCDA exemplify how different governmental bodies can work together to achieve common goals. The road dualization project, while crucial for improving transportation infrastructure, necessitated the relocation of the transmission towers to ensure the continued reliability of power supply to the FCT. This project exemplifies how careful planning and execution can minimize disruptions and ensure that critical infrastructure projects complement each other.
The TCN’s expression of gratitude to the affected customers for their patience and understanding during the relocation period reflects its customer-centric approach. Recognizing the inconvenience caused by the planned outages, the TCN aimed to complete the project as swiftly and efficiently as possible. The successful restoration of power ahead of the scheduled deadline demonstrates the company’s commitment to minimizing disruption and prioritizing the needs of its customers. This project serves as a successful case study in managing infrastructure projects that impact essential services.
This successful relocation project is not just about the technical achievement of moving transmission towers; it represents a broader commitment to infrastructural development and efficient service delivery in the FCT. The TCN’s proactive approach, transparent communication, and collaborative efforts with the FCDA have resulted in a positive outcome for the residents and businesses in the affected areas. The restored power supply will contribute to the continued economic growth and development of the region. The project’s success also highlights the importance of long-term planning and investment in power infrastructure to meet the growing demands of a rapidly developing urban center like the FCT.